HCW Crane Service

HVAC and Mechanical Lifts

Mechanical Equipment Lifts in Lake Havasu City

2 min readUpdated July 2026

Mechanical equipment lifts cover pumps, generators, boilers, water heaters, compressors, transformers, and skid-mounted assemblies. These loads usually have the mass concentrated on one side and rated lifting lugs provided by the manufacturer. Rigging to those points and getting a true hang is most of the work.

The Weight Is Never in the Middle

A generator has the alternator on one end and the engine on the other. A pump skid has the motor on one side. A packaged boiler has a heat exchanger that outweighs everything around it. Rig any of those with evenly spaced slings and the load tips the moment it clears the ground.

The manufacturer usually solves this for you with lifting lugs positioned around the actual center of gravity. Those are the points to use, and where a lift drawing exists it is worth having on site. It answers the hang question before anyone guesses at it.

Where no lugs exist, we rig to the skid or base frame and adjust sling lengths until the load hangs true at a test lift. That takes a few minutes on the ground and saves a lot of trouble in the air.

Tanks and vessels are their own case. A tank that is empty behaves nothing like one with residual product in it, and liquid that moves during the lift shifts the balance while the load is in the air. If a vessel is not confirmed empty, we plan it as though it is not.

Where It Lands and What It Lands On

Mechanical equipment tends to go into confined finished spaces. A generator pad behind a block wall. A pump in an equipment yard between a fence and a building. A water heater into a mechanical room across a patio.

That means a precise set in a tight footprint, often onto anchor bolts or an isolation pad with a specific orientation for conduit, piping, or exhaust. Orientation is worth confirming twice, because turning a heavy skid on a finished pad afterward is not simple.

Vibration isolators, spring mounts, and rails have to be in position before the equipment lands on them. If they are not there yet, we set the equipment on cribbing nearby rather than hold it in the air while somebody goes looking.

Access under the equipment is worth thinking about before it lands. Once a heavy skid is on its pad, getting rigging back underneath it means jacking or cribbing. If the same unit may need to come back out one day, leaving a way to rig it is worth five minutes now.

How the job runs

Our Process

  1. Step 1: Get the Lift Data

    Weight, lifting lug locations, center of gravity, and any manufacturer lift drawing. On generators and skids this information usually exists, so it is worth asking the supplier.

  2. Step 2: Rig and Test the Hang

    Slings to rated lugs or the base frame, lengths adjusted, then a test lift a few inches up to confirm the load hangs level before it travels.

  3. Step 3: Clear the Landing Point

    Isolators, rails, anchor bolts, and pads in place and swept. Orientation confirmed against the conduit, piping, or exhaust side.

  4. Step 4: Set and Confirm

    Slow controlled descent with tag lines, seated onto the pad or bolts, and held in the rigging until the installing crew confirms placement.

Scope

What Is Included

  • Crane and operator for pumps, generators, skids, and tanks
  • Rigging to rated lifting lugs or base frame
  • Sling length adjustment for off-center weight
  • Test lift and hang check before any travel
  • Tag line control for tight equipment yards
  • Load held in rigging until the installer confirms the set

Real HCW jobs

From the Job Site

  • Boom truck crane lifting a rooftop HVAC unit over a home driveway on a clear day
    Rooftop unit lifted over a driveway
  • Rooftop HVAC unit on a pallet hanging from the crane line high above a commercial parking lot, boom truck below
    Rooftop HVAC unit in the air
  • HCW boom truck crane on outriggers and cribbing swinging an HVAC unit over a red tile roof
    HVAC unit swung over a tile roof
  • White boom truck crane lifting a rooftop HVAC unit toward a red tile roof beside a tall palm
    Rooftop unit headed for a tile roof
See all job photos

Answers

Frequently Asked Questions

Do you need the manufacturer lift drawing?

Not always, but it helps a lot on generators, boilers, and skid packages. It tells us the lug locations and the real center of gravity, which is the thing most likely to be misjudged.

What if the equipment has no lifting points?

We rig to the skid or base frame and adjust sling lengths until it hangs true at the test lift. What we do not do is sling across the equipment itself and hope.

Can you set a generator on its pad and bolts?

Yes. Have the anchor bolts, isolators, or rails in place beforehand and confirm which side the conduit and exhaust need to face. The set itself is slow and guided.

Can you get equipment into a walled equipment yard?

That is common work. We lift over the wall or fence rather than dismantling anything, and use tag lines for a controlled descent in a tight footprint.

Ready to schedule your lift?

Tell us the load, the site and the timing. We will confirm capacity, access and a window.